This website provides updates on School District No. 43's (Coquitlam) capital projects including new school construction, seismic replacements projects, additions, and other small projects.
Updates will be posted to each project page linked in the menu to the left, and may include text, photos, videos and applicable links to other websites.
Enquiries may be directed to information@sd43.bc.ca.
Approved Projects
A project is considered approved when it receives Ministry of Education and Child Care funding.
Burke Mountain Secondary
| New School
| The Burke Mountain Secondary/Middle School contract was awarded August 19, 2024 to Yellowridge Construction Ltd. The contractor has begun work on mobilizing to site, fencing and detailed foundation excavation of the new school (September 2024).
| Fall 2026
|
Centennial Secondary
| Seismic Replacement
| NLC (Neighborhood Learning Centre) additional work completed (September 2024). | Fall 2024
|
Coast Salish Elementary
| New School
| Childcare nearing completion (September 2024).
| Fall 2024
|
École Dr. Charles Best Secondary
| Addition
| Tender for the 12 classroom addition due on September 13, Design for the 12 additional classrooms will begin soon (September 2024).
| Fall 2025
|
École Montgomery Middle
| Seismic Replacement
| Seismic replacement project approved by Ministry. (August 2024)
| Fall 2028
|
Moody Elementary
| Seismic Replacement
| Foundation work completed. Structural steel erection and glulam installation underway. Retaining walls and site access stairs being formed and poured (August 2024).
| Spring 2025
|
Scott Creek Middle
| Addition
| Second floor exterior wall panels nearing completion. Window installation complete. Interior framing complete at ground floor and boarding started. Mechanical and electrical rough-in underway at ground floor. Asphalt and paving partially complete September 2024).
| Fall 2024
|
*For a variety of reasons, planned completion dates can be revised and will be updated here if they are.