Parking lot completed (Spring 2020)
Demolition complete and construction of parking lot continues (January 2019)
Demolition almost complete and construction of parking lot continues (November 2018)
Old school demolition and construction of parking lot underway (September 2018)
Occupancy achieved and move-in underway (July 2018)
Community Celebrates Opening of New Moody Middle School (June 18, 2018)
Occupancy and move-in to occur soon (June 2018)
Moody Middle School Opening Ceremony and Open House Invitation (June 2018)
Construction is nearing completion and occupancy is expected soon (February 2018)
Construction is well underway and installation of the interior drywall
has begun (December 2016)
Structural steel for the classroom wing is nearly completed. Roofing is
expected to begin soon (September 2016)
The foundation is done. Concrete walls are almost all completed. The
suspended floor slabs are next (June 2016)
SD43 Awards Contract to Rebuild Moody Middle School
Community Open House - New Moody Middle (January 2014)
Moody Middle School Neighbourhood Learning Centre Community Consultation (April 2013)