Updates
Occupancy achieved, and addition opened to students in February. Final deficiency remediation and site clean-up is in progress (March 2025).



Roofing and glazing now complete. Breezeway connection to existing school is in progress. Interior fixtures and finishing in progress (November 2024).


Second floor exterior wall panels nearing completion. Window installation complete. Interior framing complete at ground floor and boarding started. Mechanical and electrical rough-in underway at ground floor. Asphalt and paving partially complete (September 2024).


Ground floor exterior wall panels complete. Structural steel nearing completion (August 2024).
Building Permit received. Site works
underway. (March 2024)
Working drawings are being finalized. Site preparation is beginning. (January 2024)
Ministry approval provided. Building Permit has been submitted. (December 2023)
Architect Renderings (December 2023)