The school is substantially complete and officially opened to students and staff on January 13, 2026. Remaining deficiency and warranty-related work is nearing completion, marking the final stages of the project (August 2026).

The school is substantially complete and officially opened to students and staff on January 13, 2026.  Work on the all-weather field and playground is progressing well, and crews continue to address remaining deficiency items as the project progresses through its final phase (May 2026).

The school is substantially complete and officially opened to students and staff on January 13, 2026.  Work continues on the all-weather field, playground, and remaining deficiency items as the project progresses through its final stages (March 2026).

The project is in its final stages, with teams focusing on completing outstanding work and preparing the school for occupancy.  Building commissioning, final inspections, and general project completion are ongoing. (December 2025).

The building envelope is nearing completion, and interior construction is progressing well.  Work on exterior hardscape elements is also ongoing as the project continues to advance (September 2025).

Construction of the new Moody Elementary School is progressing well, with roofing, exterior sheathing, and window installation underway.  Work has also advanced within the building, including interior wall framing, electrical rough-in, and the installation of mechanical systems (March 2025).

Structural steel installation is nearing completion, while roofing, exterior sheathing, and window installation continue to advance.  Interior work is also underway, including wall framing, electrical rough-in, and the installation of mechanical systems.  Site preparation for the future parking lot is ongoing (November 2024).

Foundation work has been completed, and structural steel erection and glulam installation are well underway.  Construction of retaining walls and site access stairs is also progressing as the project continues to take shape  (August 2024).

The foundation work is well underway. Underground services installation and slab on grade preparation are ongoing. (March 2024)

Building foundations are underway. (January 2024)

Site works for the new school are ongoing (September 2023)

Contractor Selected (June 2023)

A contractor has been selected for the new seismic replacement building of Moody Elementary School.  The work will begin summer 2023 and will involve construction of a new building, play space, and parking lot on the northern portion of the École Moody Middle School of the Arts site. 

The School District is working closely with the City and the Contractor on ensuring safety, building permit, and bylaw protocols are in place.

A contractor has been selected for the new seismic replacement building of Moody Elementary School.  The work will begin in the summer of 2023 on the northern portion of the École Moody Middle School of the Arts site. (June 2023)

Moody Elementary - Architect Video Rendering (May 2023)

Building permit received, project is out to tender (April 2023)

Moody Elementary Updated Renderings (September 2022)

Building Permit Submitted (July 2022)

Open House Photos (June 2022)

Moody Elementary Open House Boards (June 2022)

Moody Elementary Tricity News Ad (June 2022)

Moody Elementary Open House Poster shared with families (June 2022)  

Working Drawings Underway (June 2022)

Development Permit Submitted (June 2022)

Detailed Design Development Drawings Underway (January 2022)

Schematic Design Drawings Underway (Summer/Fall 2021)

BC Gov News Press Release (June 2021)