Hazel Trembath Elementary

This webpage provides information and updates on Hazel Trembath Elementary, specifically as they relate to the school site. For information on school programs, please visit Hazel Trembath Elementary.

Updates (from newest to oldest)

hazel-3.6b545812806.png

The design phase for Hazel Trembath is now complete, and the project is in the final stages of the tender process.  Groundbreaking for the construction is anticipated in the coming weeks as the project moves into the next phase (August 2026).

The design process is progressing, with approximately 70% of the design work now complete.  A community open house was held on April 30, 2026, to share the proposed site plan and conceptual design renderings of the new school.  The Environment Design Permit has been approved by the Port Coquitlam Council (May 2026). 

The design process is progressing, with approximately 50% of the design work now complete.  Site preparatory work is ongoing in advance of future construction.  A community Open House is anticipated in April or May to share the proposed site plan and conceptual design of the new school (March 2026)

The design process for the new Hazel Trembath Elementary School is underway.  Engagement with the City of Port Coquitlam and project consultants continues as planning and design progress (December 2025).

Province approves plan to rebuild Hazel Trembath Elementary

Project Definition Report (Business Case) submitted to Ministry. Demolition and clean-up of original site complete (June 2024).

Project Definition Report (Business Case) is underway. (December 2023)

Demolition and clean up begins as site is released to district. (December 2023)

Suspicious fire guts B.C. elementary school, plans underway for students and teachers - TriCity News (October 15, 2023)